Roadwork and sidewalk replacements in the Angus subdivision (Birch Drive and 56th Street) will begin over the upcoming weeks.
Access: Single lane alternating traffic will be maintained throughout construction and Emergency services access will be maintained at all times. The work is limited to surface improvements. Please obey all detours and traffic signage.
Parking will be available adjacent to the work zone.
Construction hours are typically 7:00 a.m. to 7:00 p.m., but work may extend to 9:00 p.m. NRRM Noise Control Bylaw No. 19 (2009) will be followed.
Planned Construction Schedule:
| BLOCK | ANTICIPATED SCHEDULE |
| 56 Street (removals) | July 17-31 |
| Birch Drive (removals) | July 17-31 |
| Concrete Placement | First Week of August |
| Asphalt Paving | First half of August |