The 2018 Capital Projects for Wastewater (Sanitary Sewer) Systems include:

Sewer Outfall Relocation - Part 2 In-River Works

Budget:

Funding Sources:

Construction Start Date:

 

Updates:

$5,000,000

NRRM Province of BC

December 2017

Outstanding work: 

  • The in-river portion of outfall construction is expected to take place during the 2017/2018 winter months when the Muskwa River levels are at their lowest.
  • The remaining outfall piping installation and siteworks are expected to continue in spring 2018, with Substantial Completion being achieved by September 2018.

Work in 2017 included: 

  • Clearing of outfall right of way in March 2017.
  • Outfall tendering in April 2017. 
  • The land portion of the 2.3 km pipeline commenced in August 2017. 
  • Drainage works completed in Watercourse 1 near WWTP
  • Outfall piping and manholes installed from MH S-1 to MH S-7

Work in 2016 included: 

  • Detailed design drawings and preparation of tender documents completed in March 2017. 
  • Applications for permits, licences and other approvals completed for construction phase. 
  • Pre-design and environmental impact study (EIS) completed. 